Capacity of Renesas’s Naka factory has returned to 100% of pre-fire level

Update: June 26, 2021

Renesas Electronics today announced an update regarding production capacity recovery following the occurrence of a fire on March 19, 2021 at part of the processes in the N3 Building (300mm line) of Naka Factory.

The announcement stated that the start-up of all necessary manufacturing equipment to recover pre-fire production capacity of the N3 Building, which resumed operation on April 17, has been completed. As a result, the production level of the N3 Building has returned to 100% of the pre-fire level as of the evening of June 24. In addition, alternative production is contributing to Renesas’ manufacturing as planned.

Renesas expects that the shipment level of the products manufactured in the N3 Building to return to pre-fire level around the third week of July. However, this shipment level refers to that of the N3 Building as a whole. Therefore, the recovery timing of the shipment level may vary from product to product.